Should you pay builders a deposit? Usually yes, but a small one, tied to something you can see, and never the bulk of the job before work starts. A deposit is reasonable when it pays for materials the builder has to order in your name, or secures a start date months ahead. It is a warning sign when it is large, demanded in cash, or asked for before you have a written quote and contract.
No UK law sets a maximum deposit for home building work, so the protection comes from how you structure the payments. This page sets out what is normal, how to pay so you keep your rights, and what to do if a builder takes the money and does not turn up. It is written for homeowners in Kent, but the rules apply across England.
How much deposit is normal for a builder?
There is no official figure. In practice, builders’ approaches fall into three groups:
- No deposit: established firms on smaller jobs often ask for nothing up front and invoice at stages or on completion.
- A small booking deposit: often around 10% of the price, to hold a slot in the diary.
- A materials deposit: on jobs with expensive made-to-order items (bifold doors, a kitchen, roof lights, a staircase), a builder may ask you to pay for those items before ordering them.
A request for half or more of the total before anything happens on site is where homeowners get hurt. If the builder cannot fund the first week of labour and materials, that tells you something about the business.
Paying for materials: the safer way
If a large share of the upfront money is for materials, you have options that protect you better than handing over cash:
- Pay the supplier directly, with the order in your name and delivery to your address.
- Ask for the supplier’s invoice or order confirmation before you pay the builder for those items.
- For made-to-measure items, get the specification in writing first, because made-to-order goods may not come with a cooling-off period.
How to structure payments on a building job
The principle that protects you is simple: at any point in the job, you should not have paid for more than has been done and delivered. A stage payment schedule written into the contract does this. A typical extension might look like this:
- Deposit or materials payment on signing, kept small.
- Foundations and slab complete, after building control has inspected them.
- Walls to roof level.
- Roof on and watertight.
- First fix (electrics and plumbing run, before plastering).
- Second fix and finishes.
- Retention held back until snagging is complete.
Tie each stage to something you can check, not to a date. “Week four” can pass with nothing built; “roof felted and tiled” cannot. If a stage needs a building control inspection, pay after it passes. Our page on comparing builders’ quotes covers the lines a quote should include so these stages can be written in from the start.
Keep a retention
Holding back a small percentage of the final payment until the snagging list is cleared gives the builder a reason to come back for the last small jobs. Agree the amount and the release date in the contract so it does not look like you are withholding money unfairly. For more on that last stage, see when to pay a builder’s final payment.
Pay by credit card if you can
How you pay matters more than how much. Under Section 75 of the Consumer Credit Act, if you pay at least part of the cost on a credit card and the item or service costs over £100 and up to £30,000, the card provider is jointly liable with the trader. Citizens Advice notes that the limits apply per item, and that you can claim the full cost even if only part of it went on the card.
That makes a credit card ideal for a deposit: put the deposit on the card, and if the builder disappears with it, you can claim from the card company. Check the job is paid directly to the business on your card, because Section 75 usually does not apply if you pay through a third party.
Debit card payments do not get Section 75, but you can ask your bank for a chargeback. Bank transfers have the least protection of all, and cash has none. If a builder insists on cash for the deposit, or offers a discount for it, that is a reason to walk away.
Your cooling-off rights on a deposit
If you sign a contract with a builder in your own home, you normally get a 14-day cooling-off period. According to Citizens Advice:
- If you cancel within 14 days and the work has not started, you can get all your money back, deposit included.
- If you asked the builder to start during the cooling-off period, you may have to pay for the work done so far.
- If the builder did not give you cancellation information, the cooling-off period is extended by 14 days from when you receive it, up to a maximum of a year.
- Made-to-measure items and urgent repairs you called the trader in for may not come with a cooling-off period.
This is one more reason to keep the deposit small and the start date after the 14 days, unless the job is genuinely urgent.
Checks before you pay anything
- Written quote and contract with the full price, the payment stages, the start and finish dates, and what happens if either side cancels.
- A real business address and a landline or company details you can check. A mobile number and a first name are not enough.
- Insurance: ask for proof of public liability cover.
- References you can visit, ideally a job finished in the last year.
- A vetted scheme: Kent County Council runs Trading Standards Checked, a list of traders who have been checked by Trading Standards. A trader being on it is not a guarantee, but it means someone has looked.
- Bank details in the business’s name, matching the name on the contract. Be wary of last-minute changes to bank details sent by text or email, and confirm them by phone on a number you already have.
What if the builder takes the deposit and does not start?
- Put it in writing. Email or write giving a firm start date, and say you will treat the contract as ended if they miss it.
- Claim from your card provider if you paid by credit or debit card: Section 75 or chargeback.
- Get advice from Citizens Advice, which can refer the case to Trading Standards.
- Consider the small claims track if the sum is worth recovering and the business still exists.
- Report fraud if the trader has vanished or was never a real business.
Keep every message, invoice and receipt from the start. They are what a card company, Trading Standards or a court will ask for.
Frequently asked questions
Is it normal for a builder to ask for a deposit?
Yes. Plenty of honest builders ask for a deposit, particularly to cover materials or to book a start date. The questions are how big it is, what it pays for, and how you pay it.
Is 50% upfront too much for a builder?
For most jobs, yes. Half the price before work starts leaves you with little leverage if things go wrong. Offer a smaller deposit plus stage payments, or pay suppliers directly for expensive materials.
Should I pay a builder in cash?
Avoid it. Cash leaves no record and has no protection if the builder does not turn up. A credit card gives you Section 75 protection on payments over £100 and up to £30,000.
Is there a legal limit on builders’ deposits in the UK?
No. There is no statutory cap on deposits for home building work in England. Your protection comes from the contract, the payment method and consumer law.
Can I get my deposit back if I change my mind?
If you signed at home and cancel within the 14-day cooling-off period before work starts, you are normally entitled to a full refund. After that, it depends on the contract terms and what the builder has already spent on your job.
What should a builder’s contract say about payments?
The total price, the deposit, each stage payment and what triggers it, any retention and when it is released, and what happens to money already paid if either side cancels.
For more on planning and paying for work on your home, see the rest of Contemporary Structures.
Related guides
- Conservatory Roof Replacement vs Glass Film: Which Fixes a Too-Hot, Too-Cold Conservatory?
- Air Source Heat Pump Cost in 2026 After the £7,500 Grant: What You Actually Pay
- Do You Need Planning Permission for a Rear Extension in Kent? 2026 Permitted Development Rules
- How Much Does a Conservatory Base Cost in the UK? (2026 Price Guide)
- Do You Need a Party Wall Agreement for a Rear Extension? Cost and Rules Explained
- Underfloor Heating vs Radiators for a Home Extension: Cost, Running Bills and Which to Choose
- How Much Does a House Extension Cost in 2026? Full UK Price Breakdown
- Loft Conversion Cost and Types: Dormer, Hip-to-Gable and Velux Explained
- Kent Home Improvement News: June 2026
- House Extensions: The Complete UK Homeowner’s Guide
- Single Storey Extension Ideas, Costs and Planning Rules
- Double Storey Extensions: Costs, Designs and What You Can Build
- Side Return Extensions Explained: Cost, Light and Layout
- Kent Home Improvement News: Mid-June 2026
- Garage Conversion Guide: Cost, Building Regs and Best Uses
- Extension vs Moving House: Which Is Better Value in Kent?
- Wraparound vs Rear Extension: Cost and Space Compared
- House Extension Builders in Kent: Costs, Lead Times and How to Choose
- Conservatory Guide: Styles, Costs and How to Choose One
- Kent Home Improvement News: Late June 2026
- How Much Does a Conservatory Cost in 2026? UK Prices by Type
- Conservatory vs Orangery vs Extension: Which to Build?
- Conservatory Roof Options: Glass, Polycarbonate and Tiled Compared
- Kent Home Improvement News: Early July 2026
- How to Keep a Conservatory Warm in Winter and Cool in Summer
- Tiled Conservatory Roof Cost and Replacement Process Explained
- Conservatories in Kent: Choosing an Installer, Costs and What to Ask
- Kent Home Improvement News: Mid-July 2026
- Roofing Guide: Repairs, Replacement, Materials and Costs
- New Roof Cost UK 2026: Replacement Prices by Roof Type
- Roof Repair Cost UK 2026: Slipped Tiles and Flashing Prices
- 7 Signs Your Roof Needs Replacing (and What You Can Ignore)
- Flat Roof vs Pitched Roof: Cost, Lifespan and Best Uses
- EPDM vs Felt vs Fibreglass Flat Roofs Compared
- Kent Home Improvement News: Mid-July 2026
- Roof Tile Types Explained: Clay, Concrete and Slate Compared
- Fascias, Soffits and Guttering: When to Replace and What It Costs
- How to Find a Good Roofer: Vetting Checklist for UK Homeowners
- Roofers in Kent: Costs, How to Choose and What to Ask in 2026
- Kitchen Renovation Guide: Planning, Cost and Design in 2026
- How Much Does a New Kitchen Cost in 2026? UK Price Guide
- Kitchen Layout Ideas: Galley, L-Shape, Island and Open Plan
- Worktops Compared: Quartz vs Granite vs Laminate vs Solid Wood
- Fitted vs Bespoke vs Flat-Pack Kitchens: Cost and Quality
- Kitchen Island Ideas, Sizes and Costs: A 2026 UK Guide
- Kent Home Improvement News: Late July 2026
- Open Plan Kitchen Diner: Costs, Layouts and Knock-Through Rules
- How Long Does a Kitchen Fitting Take? Realistic UK Timeline
- Kitchen Fitters in Kent: Costs and How to Choose (2026)
- Bathroom Renovation Guide: Planning, Cost and Layout
- New Bathroom Cost 2026: What You’ll Pay in the UK
- Kent Home Improvement: Roofing Costs Rise (Aug 2026)
- Small Bathroom Ideas: Layouts That Feel Bigger
- Wet Room Cost 2026: £2,000 to £9,000 Fitted, by Size
- En Suite Cost and Minimum Size: £4,000 to £10,000 in 2026
- Kent Home News: £9,000 Heat Pump Grant Now Open
- Electric vs Mixer vs Power Shower: What Your Boiler Allows
- Bathroom Underfloor Heating Cost: 16p an Hour to Run
- Window Replacement Cost 2026: £350 to £600 Per uPVC Window
- uPVC vs Aluminium Windows: the 1.4 U-Value Rule
- How Long Does a Bathroom Take to Fit? 5 to 10 Working Days
- Home Improvement News: Solar Up 14%, Heat Pumps Down 17%
- Double vs Triple Glazing: Part L Still Stops at 1.4
- Bathroom Fitters in Kent: What to Ask Before You Pay
- Sash Window Repair or Replace? What Kent Councils Allow
- Bifold vs Sliding Doors: What Building Regs Actually Set
- Composite Door Cost 2026: £550 to £2,350 Fitted
- Window Energy Ratings: Band B Is the Rule, Not C
- Replacement Windows: the 1.4 U-Value and Vent Rules
- Double Glazing Kent: the 1.4 U-Value Every Quote Must Hit
- Heat Pumps in Kent: the £7,500 Grant and the 1.5m³ Rule
- Heat Pump vs Gas Boiler: Break-Even Is a SCOP of 3.0
- Permitted Development Rights: The 8m Rear Extension Rule
- Air Source vs Ground Source Heat Pump: £13k or £26k?
- Kent Home News: Council Merger Paused, Heat Pump Bids Up 81%
- Building Regulations Approval: Kent Fees, 10-Year Rule
- Boiler Upgrade Scheme: £9,000 Grants From 21 July 2026
- New Boiler Cost 2026: £1,800 to £4,500 Fitted
- Do Heat Pumps Work in Old Houses? Yes, With 3 Conditions
- Heat Pump Installers in Kent: 8 Checks Before You Sign
- House Rendering in Kent: When the Wall Must Be Insulated
- What Is TrustMark? The Kent Trade Badges That Count
- Home Improvement Grants in Kent: ECO4 Ends 31 December
- Kent Home News: Heating Oil to Be Regulated, £9,000 Grant
- Conservation Area Planning Rules: The 3m Rear Limit
- How to Apply for Planning Permission in Kent: £548, 8 Weeks
- Best Kitchen Cupboard Paint: Match It to the Door Surface